Big break on bidding

Proposals for Route 219 project are lower than anticipated

HOLLIDAYSBURG — Work could begin as soon as October on the first major construction phase of the long-awaited

Route 219 South extension after bids came in lower than expected Thursday.

Joseph B. Fay Co. in suburban Pittsburgh is the apparent low bidder at $110,468,000 for excavation and preliminary construction along the entire 11-mile extension from Somerset to Meyersdale.

“This is great news,” PennDOT District Executive Tom Prestash said Thursday after the virtual bid opening at District 9 headquarters in Hollidaysburg.

“This is the day we have been waiting for for the last 40 years,” Somerset County Commissioner John Vatavuk said at the PennDOT office.

Fay is based in Tarentum, Allegheny County, but also uses an address in nearby Russellton.

Fay edged out Somerset County-based New Enterprise Stone & Lime Corp., which submitted the second-lowest bid at $123,835,354.99.

“We are disappointed New Enterprise didn't get it,” Vatavuk said. “They have a plant right in Somerset, and they are based out of Somerset County. A lot of people in Somerset County work for New Enterprise.”

Others bidding included Lane Construction Corp. and Beaver Excavating Co.

PennDOT can’t give companies preferential treatment based on location, Prestash said, adding that the state is pleased that Fay submitted a bid that was lower than engineers’ estimated cost.

Bid documents will be reviewed and bond information verified before the contract is awarded, Prestash said.

Once the bid is verified and a contract awarded, the successful bidder will be given the notice to proceed, said Jim Pruss, portfolio manager. That notice could be finalized by Sept. 23, he said.

“They can start immediately after receiving that notice,” Prestash said.

But the contractor will be required to obtain a waste permit, identifying what it will do with about 5 million yards of rock and soil it will have to remove along the new highway’s route, Pruss warned.

“You may not see dirt flying immediately in September,” Pruss said. “But there is some work they can do before they have to have that permit.”

The new four-lane limited access highway from Somerset to Meyersdale currently is the largest new road-building project in the state.

Two more rounds of bidding will be needed over the course of the four-year project in order to complete all three phases.

Electronically submitted bids “opened” Thursday on the PennDOT computers are available for public review online.

The first phase will primarily involve excavation and grading to lay out the future roadbed. Because the construction will require the realignment of several existing township and state roads, those roads will be rebuilt and paved, along with a new interchange at the southern end of the new road, Pruss said.

Doing that work now, rather than waiting until the final paving contract, will help with traffic control in the construction areas and speed up the overall project, he said.

PennDOT designers expect that the contractor will work on the Meyersdale interchange early in the project, making it the most visible construction for most of the public.

The second phase contract is to be awarded and work will begin while the first phase contractor is wrapping up. That phase will focus on construction of several bridges along the route.

Finally, the third phase contract will also overlap with the second phase. The final contract is the actual road construction, Pruss said.

The Route 219 extension to Meyersdale has been in the planning and design process since at least 2006, with land acquisition beginning in 2009 and wrapping up last year, project engineer Greg Illig said.

But Somerset County leaders have been pushing for the extension since the four-lane highway opened north to Johnstown in the 1970s, Vatavuk said. Working with Maryland planners, Vatavuk said Somerset plans to continue to lobby for the final seven-mile link between Meyersdale and Interstate 68 in Maryland.

PennDOT currently has no money identified for that work, Prestash said. A pool of federal highway fundsremaining from the defunct Appalachian Development Highway Program is being prioritized for about $2 billion to $3 billion in projects formerly eligible for the program.

 

Click here to subscribe to The Tribune-Democrat print edition.

Click here to subscribe to The Tribune-Democrat e-edition.

 

1
Text Only | Photo Reprints
Local News
  • Flower2 Flowers' color doesn't have to fade

    Those pots of bright yellow daffodils, Easter lilies and hyacinths gracing the home this weekend do not have to end up in the trash bin when the blooms start to fade.

    April 20, 2014 2 Photos

  • Refinancing could lower Richland School District's debt by $2.2M

    When Richland School District borrowed funds for its high school project a decade ago, board members circled “2014” on their calendars as a likely first option to refinance the debt.

    April 20, 2014

  • Pipeline to carry shale byproducts

    An 8-inch transmission line crossing Pennsylvania, including four municipalities in Cambria County, is being repurposed to carry some of the by-products from Marcellus and Utica shale production.

    April 20, 2014

  • Judge Creany, Timothy Vets courts gain support

    Signs of success are mostly anecdotal in Pennsylvania’s special courts for veterans, but judicial officials and lawmakers are so convinced of the program, they’re lobbying to expand it.

    April 20, 2014 1 Photo

  • pow21 Person of the Week: ‘I wanted to help’: Teen uses birthday to show love for children, animals

    Anastasia Machik’s love for children and animals inspired her to forgo her birthday gifts for the sake of the two.

    April 20, 2014 1 Photo

  • Students taking steps to call attention to child abuse

    An upcoming community walk will help raise awareness of child abuse.

    April 20, 2014

  • In brief: PennDOT reports weekly work schedule

    April 20, 2014

  • District Deaths April 21, 2014

    April 20, 2014

  • Halfway house inmates can ease back into society

    Prison life can be a time warp.
    When inmates are locked away – for months, years, decades – society moves forward: Technology evolves, major events occur, pop culture changes. From a personal perspective, families and friends live their lives: weddings, funerals, graduations, births, retirements. All the while, criminals bide their time, existing in a regimented world of cement walls and metal bars.
    Almost all of them eventually rejoin society, though.

    April 19, 2014

  • Crime board took aim at house

    Johnstown’s unemployment rate is around 8 percent.
    One-third of the city’s population lives in poverty.
    Burglaries and assaults significantly increased between 2010 and 2012. There is a thriving illegal trade in heroin and prescription drugs.
    Given those conditions, it can be challenging for Johnstown Community Corrections Center residents to find jobs when living in the facility or to avoid falling back into a criminal lifestyle upon their release.

    April 19, 2014

Poll

Would you like to see the Johnstown Community Corrections Center remain open after its lease runs out on Oct. 11, 2015?

Yes
No
I'm not sure
     View Results
House Ads